The work involves demolition, disposal, and replacing the diesel fuel supply system that feeds the jail emergency generator.  Secondary containment on the piping and electronic monitoring are part of the project.  The engineers estimate for construction is $53,000.  Each bidder must be licensed as required by law.  Per Addendum 1, Contractor shall possess a A or C-36 license. Sealed bids will be received until 3:30 P.M. on Thursday, October 2, 2014 (per Addendum 3) no bids will be accepted after 3:30 P.M. One mandatory pre-bid site visit for Contractors bidding the project is scheduled for Tuesday, August 12th at 10:00 A.M.  Contractors must submit a Visitor Security Form by August 5, 2014.  Print, view, or download Notice to ContractorPrint, view, or download Visitor Security FormPrint, view, or download Plans and SpecificationsPrint, view, or download Addendum 1 07-03-14. Print, view or download Walk though list 08-12-14Print, view, or download Addendum 2 08-25-14Print, view, or download Addendum 3 09-02-14Print, view or download Addendum 4. Print, view, or download Addendum 5 09-29-14

Bids are currently being evaluated.

 

Contractor

Total Base Bid

Add Alternate

Paradiso Mechanical

$139,820

$28,500

Bell Products

$143,708

$26,377

 